Package- A (Unit-01): Construction of 150M height RCC Single Flue Chimney complete in all respect including pile & pilecap works, fabrication and erection of steel flue cans, installation of Borosilicate Glass Block Lining on Inner Surface of Steel Flue CAN, erection of shop fabricated structural platforms, installation of electrical items in conformity with the approved layout etc to complete the chimney in all respect as per TCC for Unit-01 Chimney at 2x500 MW NTPC Mauda Stage-I FGD Package.
and
Package- B (Unit-02): Construction of 150M height RCC Single Flue Chimney complete in all respect including pile and pilecap works, fabrication and erection of steel flue cans, installation of Borosilicate Glass Block Lining on Inner Surface of Steel Flue CAN, erection of shop fabricated structural platforms, installation of electrical items in conformity with the approved layout etc to complete the chimney in all respect as per TCC for Unit-02 Chimney at 2x500 MW NTPC Mauda Stage-I FGD Package.