BHEL's
Steam Generators account for 1,110 MW of the
operating Thermal capacity in Malaysia. Boilers
(60 MW) were supplied to for the National
Electricity Board (NEB) of Malaysia for their Tanku Ja'afar Power Station in the early 1970s.
The major projects executed are:
|
|
 |
12 boilers (up to 120 MW) for NEB for Gas conversion/
Rehabilitation. |
 |
Turnkey execution of 2x120 MW Tripoli West Power Station (extension) in Libya. |
 |
Rehabilitation of a boiler at the Tripoli West Power Station (installed by a European supplier) |
 |
2x60
MW Turbine Generators & auxiliary equipment for
Delimara Power Station, Malta. |
 |
2x60
MW Turbine Generator & Ancillary equipment for
Dhekelia `B' Station in Cyprus. |
 |
Boilers
for 2x30 MW Al-Arish Power Station in Egypt. |
 |
Supply of intricate high-temperature application castings and condenser for 800 MW sets to Russia. |
 |
Wear-resistant
ceralin-lining system for coal mills for a French
company. (Power plant located in South East Asia) |
 |
Orders
executed for reputed manufacturers like Mitsubishi Heavy
Industries, Japan, Combustion Engineering, USA, and Pyro
Power Corporation, USA, for supply of Pressure Parts for
boilers for projects in Egypt, China, USA, etc. |
 |
Supply of critical components for large generators to Siemens, Germany. |